TNBG Serdang

Our Mission Contact Services Job in Progress News Reference Job Child Guard View

Up CHS 11KV Reroute TNBG Serdang PTP SCADA Taman Wawasan TNBG Earthing TNBD FOC IHI PK 3 Lighting Defect IEEE Testing U6 Overhaul TNBG TT-4 Retrofitting

 

TNBG Serdang - Flowmeter Installation.

Saftech was awarded a contract to install Ultrasonic Flow meter for TNBG Serdang Power Station. Scope of works is to dismantle existing flowmeter and install new flowmeter. Works is expected to start around mid March and expects to complete around mid June 2003.

Progress Work